36-Inch, 10-Week Pickling at 850 psig

Stories

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
Share
Texas, USA
36-inch diameter
850 psig
10-week pickling operation

A major Texas midstream operator was preparing to commission a new 36-inch transmission line, 64 miles long, designed to carry an average of 17 million standard cubic feet per hour at 850 psig. Before the line could carry odorized gas to downstream customers, the interior of the pipe had to be conditioned. Fresh steel reacts with mercaptan. Mill scale, rust, and the inherent reactivity of new pipe surfaces would strip odorant from the gas stream and produce odorant readings at the downstream end well below the regulatory detectability standard.

Rushing the line into service without conditioning was not an option. The operator needed a pickling strategy that would saturate the reactive sites along the full 64 miles, stabilize odorant consumption at a predictable rate, and produce the documentation a regulator would expect to see at audit.

Approach

MRR designed an online pickling operation built around elevated upstream odorant injection and continuous monitoring at the downstream end. Six temporary odorizers were staged at the front of the pipeline, set to inject at concentrations several times the operator’s normal target. The elevated rate provided the headroom needed to overcome reactive losses along the full 64-mile length while still delivering odorized gas to the downstream connection.

Flow measurement on a transmission line of this size required equipment that could be installed without breaching the pipe. MRR deployed ultrasonic clamp-on flowmeters at the upstream injection point, providing accurate flow data for proportional odorant control without any modification to the line itself. Solar-powered flow controls allowed the temporary odorizers to operate in the remote sections of the route without tying into utility power.

Monitoring at the downstream end tracked odorant concentration in real time over the full 10-week operation. As the pipe interior conditioned and reactive losses dropped, the upstream injection rate was reduced in stages. The operation concluded when the downstream concentration tracked the upstream concentration within an acceptable margin and held there.

Outcome

The line was successfully conditioned over 10 weeks of continuous operation. Approximately 5,500 gallons of Scentinel E odorant was consumed during pickling — the volume required to saturate the reactive surface area of 64 miles of fresh steel pipe at this diameter. At the end of the operation, the pipeline transitioned to normal service with stable odorant consumption and downstream readings within the operator's approved detectability specification from the first day of commercial operation.

The documentation produced through the operation — upstream and downstream concentrations, equipment settings, flow data, daily logs — became part of the line's commissioning file, giving the operator a documented record to support regulatory review.

MRR runs pickling operations across pipe sizes from distribution laterals to large transmission lines. The 64-mile Texas line sits at the upper end of that range; a 4-inch lateral commissioning operation runs on the same principles at a fraction of the duration.

Upward view of a modern high-rise apartment tower in Manhattan with reflective glass windows and protruding balconies against a blue sky.
Manhattan Odor Fade Resolution

Odor fade in the new gas piping of a Manhattan high-rise, eliminated in two weeks with no odorant intentionally released to the neighborhood.

MRR enclosure tent reading "Your End-to-End Gas Odorization Partner," connected to hoses and blower equipment for an atmospheric-isolated soil excavation, with safety cones in the foreground.
Large Mercaptan Spill Remediated

More than 400 odor calls, seven figures a day in potential lost revenue, and mercaptan underground beside active waterways.

Small tan modular gas odorization building connected to storage tanks and piping at a rural renewable natural gas site, with utility poles in the background.
RNG Building, 3-Month Commission

A modular RNG odorization building, manufactured off-site and commissioned at a Quebec injection point on a three-month schedule.

Technician in blue coveralls with reflective safety striping adjusting a temporary gas odorization skid and tank at a fenced outdoor site.
Emergency Temporary Odorization

Maintaining odorization compliance for three months while a failed permanent system was redesigned, fabricated, and installed.

Refinery storage tank being decommissioned at an industrial site in Illinois.
5,000-Gallon Tank Decommissioning

Replacing a 5,000-gallon ethyl mercaptan tank at a refinery, with 1,800 gallons of odorant held and returned to service.

On-site incineration equipment used to drain and treat over-odorized liquid from a 12-inch transmission line in Quebec
12-Inch Odorant Drain and Incineration

Excavating, tapping, and draining liquid odorant from a 12-inch transmission line — two-week response with on-site incineration.

C1D1-rated dual-odorizer trailer, a custom-built mobile gas odorization unit, at an industrial site in Illinois.
C1D1 Dual-Odorizer Trailer

A dual-odorizer trailer with integrated filtration, flow telemetry, and C1D1-rated systems — 20 weeks from order to delivery.

Row of portable flare units operating at night to generate flow for an inline pipeline inspection campaign in northern Ontario
Six-Week Flow Generation

Portable flow generation supporting an inline inspection campaign in northern Ontario — 12 to 16 hours a day across six weeks.

Natural gas pipeline conditioning equipment at a shopping mall construction site in New Jersey.
New Jersey Mall Gas Line Conditioning

Conditioning new gas lines inside a mall under construction — with continuous monitoring that surfaced previously undetected leaks.

1,000-gallon modular gas odorization building installed at a site in Georgia.
1,000-Gallon Modular Building

A 1,000-gallon modular odorization building, fabricated at the MRR shop and set on its foundation as a single integrated unit.

Natural gas odorization equipment being decommissioned across four stations at a site in Nebraska.
Four-Station Retirement, 2,300 Gal.

Retiring odorization infrastructure across four stations, recovering 2,300 gallons of odorant for continued service.

Storage tanks being decommissioned following a lightning-strike fire at a natural gas site in Alabama.
Three-Tank Decommissioning

Stabilizing and decommissioning three tanks damaged in a suspected lightning-strike fire, four days from mobilization to closure.

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
5-Month RNG Commission

Custom design, manufacturing, and commissioning of a renewable natural gas odorization system, delivered in five months end to end.

1980s-era underground storage tank being cut down and removed at a site in Michigan.
1980s Tank Removal

Removing a 1980s-era underground bulk odorant tank too large to transport — treated and cut down for removal entirely on site.

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
36-Inch, 10-Week Pickling at 850 psig

Conditioning a new 36-inch, 64-mile transmission pipeline over 10 weeks of continuous online pickling at 850 psig.