4,800-Gallon Odorant Drying, Two Sites

Stories

Share
Canada
•
4,800 gal dried, cloud point restored to −47°C or better
•
72% lower cost than disposal — ~$387,000 CAD saved
•
Two site visits, September 2026

A Canadian natural gas utility identified water contamination in the bulk mercaptan odorant tanks at two of its power generation sites. The odorant at both sites is supplied to a manufacturer cloud point specification of −45°C or colder; water ingress raises cloud point, and once a sample clouds above −45°C the product is off specification. The conventional path for off-spec odorant is to pull it from service, ship it as hazardous waste for incineration, and replace the inventory.

At Site A, 3,200 gallons had drifted to a 0°C cloud point, with roughly half an inch of free water standing at the bottom of the tank. At Site B, 1,600 gallons showed the same 0°C cloud point, with about an inch of free water. Neither volume was a candidate for replacement without real cost and downtime, and both needed a path back to spec rather than disposal.

Approach

MRR deployed Arida™, its multistage adsorption process for water-contaminated mercaptan odorant, across two site visits in September 2026 - one odorant volume per site, treated independently.

At each site, the contaminated odorant was processed through the Arida system to remove the ingressed water and bring the product back within the manufacturer's cloud point specification. Cloud point was determined before and after treatment per ASTM D2500, the standard method for this measurement, giving a verifiable before/after result rather than a visual or field estimate.

Site A's 3,200 gallons came back to a −47°C cloud point, with roughly 9.0 gallons of water removed. Site B's 1,600 gallons came back to −49°C, with roughly 11.5 gallons removed — in both cases comfortably inside the −45°C limit. The dried odorant was returned directly to each site's bulk tank rather than trucked off site for replacement product, keeping both locations on their existing inventory.

Outcome

Across both sites, MRR dried a combined 4,800 gallons of odorant and returned it to service at a cloud point of −47°C or better. Treating in place rather than disposing and replacing cut the variable cost by an estimated 72%, or roughly $387,000 CAD, based on the service rates and disposal/replacement fees applicable to this project — a comparison that excludes Arida's job-level fixed costs and the methanol tank wash required under either approach.

Avoiding incineration of the recovered odorant also kept an estimated 12.0 short tons of sulfur dioxide out of the atmosphere, calculated from the sulfur content of the volume processed assuming complete combustion (manufacturing emissions for replacement product aren't included in that figure).

Water contamination in bulk odorant tanks is a recurring field issue, most often traced to leftover hydrotest water in new tanks, incomplete drying at commissioning, carryover during internal transfers, or a water-based pump flush purged into the bulk tank. Where contamination is caught before extensive dilution, Arida gives operators a way to recover the existing inventory rather than defaulting to disposal — a materially different cost and waste profile than the replace-on-contamination approach the industry has typically relied on.

4,800-Gallon Odorant Drying, Two Sites

MRR dried 4,800 gallons of water-contaminated odorant across two power generation sites and returned both to spec at 72% lower cost than disposal and replacement.

Upward view of a modern high-rise apartment tower in Manhattan with reflective glass windows and protruding balconies against a blue sky.
Manhattan Odor Fade Resolution

Odor fade in the new gas piping of a Manhattan high-rise, eliminated in two weeks with no odorant intentionally released to the neighborhood.

MRR enclosure tent reading "Your End-to-End Gas Odorization Partner," connected to hoses and blower equipment for an atmospheric-isolated soil excavation, with safety cones in the foreground.
Large Mercaptan Spill Remediated

More than 400 odor calls, seven figures a day in potential lost revenue, and mercaptan underground beside active waterways.

RNG Building, 3-Month Commission

A modular RNG odorization building, manufactured off-site and commissioned at a Quebec injection point on a three-month schedule.

Technician in blue coveralls with reflective safety striping adjusting a temporary gas odorization skid and tank at a fenced outdoor site.
Emergency Temporary Odorization

Maintaining odorization compliance for three months while a failed permanent system was redesigned, fabricated, and installed.

5,000-Gallon Tank Decommissioning

Replacing a 5,000-gallon ethyl mercaptan tank at a refinery, with 1,800 gallons of odorant held and returned to service.

On-site incineration equipment used to drain and treat over-odorized liquid from a 12-inch transmission line in Quebec
12-Inch Odorant Drain and Incineration

Excavating, tapping, and draining liquid odorant from a 12-inch transmission line — two-week response with on-site incineration.

C1D1-rated dual-odorizer trailer, a custom-built mobile gas odorization unit, at an industrial site in Illinois.
C1D1 Dual-Odorizer Trailer

A dual-odorizer trailer with integrated filtration, flow telemetry, and C1D1-rated systems — 20 weeks from order to delivery.

Row of portable flare units operating at night to generate flow for an inline pipeline inspection campaign in northern Ontario
Six-Week Flow Generation

Portable flow generation supporting an inline inspection campaign in northern Ontario — 12 to 16 hours a day across six weeks.

Natural gas pipeline conditioning equipment at a shopping mall construction site in New Jersey.
New Jersey Mall Gas Line Conditioning

Conditioning new gas lines inside a mall under construction — with continuous monitoring that surfaced previously undetected leaks.

1,000-gallon modular gas odorization building installed at a site in Georgia.
1,000-Gallon Modular Building

A 1,000-gallon modular odorization building, fabricated at the MRR shop and set on its foundation as a single integrated unit.

Four-Station Retirement, 2,300 Gal.

Retiring odorization infrastructure across four stations, recovering 2,300 gallons of odorant for continued service.

Storage tanks being decommissioned following a lightning-strike fire at a natural gas site in Alabama.
Three-Tank Decommissioning

Stabilizing and decommissioning three tanks damaged in a suspected lightning-strike fire, four days from mobilization to closure.

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
5-Month RNG Commission

Custom design, manufacturing, and commissioning of a renewable natural gas odorization system, delivered in five months end to end.

1980s Tank Removal

Removing a 1980s-era underground bulk odorant tank too large to transport — treated and cut down for removal entirely on site.

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
36-Inch, 10-Week Pickling at 850 psig

Conditioning a new 36-inch, 64-mile transmission pipeline over 10 weeks of continuous online pickling at 850 psig.