Four-Station Retirement, 2,300 Gal.

Stories

Natural gas odorization equipment being decommissioned across four stations at a site in Nebraska.
Share
Nebraska, USA
Four station sites
2,300 gallons of odorant relocated
Six days on-site

A natural gas distributor in Nebraska had reached the point in its asset planning where four legacy odorization stations needed to be decommissioned together. The scope across the four sites included a 5,000-gallon underground bulk odorant storage tank, a 1,000-gallon underground tank, a 3,000-gallon aboveground tank, multiple smaller tanks ranging from 32 to 150 gallons, and the odorant pumps and associated equipment at each station.

Approximately 2,300 gallons of usable odorant were held across the four sites and needed to be consolidated to a single alternate station so it could continue in productive service rather than being treated as waste. The project required coordination across multiple geographic locations, sequencing that respected the operator’s ongoing distribution requirements, and subcontractor management for the excavation and crane work required at the underground tank sites.

This was not single-station decommissioning. It was a coordinated retirement of a portion of the operator’s fleet, planned and executed as one project.

Approach

MRR organized the project as a multi-site campaign rather than four separate engagements. The planning phase produced a site-by-site scope, a unified equipment and material disposition plan, a consolidated odorant transfer sequence routing 2,300 gallons from four origin sites to a single destination station, and an integrated documentation package that would close the full project at the end.

Two MRR field crews operated in parallel across the four sites to compress the on-site duration. MRR contracted a local excavation and crane company as a subcontractor for the digging and lifting work at the underground tank sites, with MRR supervising the subcontractor's work and integrating it into the broader decommissioning sequence. An MRR odorant delivery truck was dedicated to the project for the duration of the on-site work, handling the filter-transfer operations at each origin site and the consolidated delivery to the alternate station.

The underground tanks at each site were exposed by the subcontractor crew, then disconnected, drained, and decommissioned by MRR technicians. The aboveground tanks and smaller equipment were processed in parallel. The contaminated piping at each site was identified, isolated, and removed as part of the station-specific scope.

Outcome

The full fleet retirement was completed with two MRR crews on site for six days and the odorant delivery truck on site for four days. The entire 2,300-gallon volume of recovered odorant was successfully relocated to the alternate utility station, where it continued in productive use rather than being treated as waste material. The decommissioned tanks and equipment were transported to MRR's Philippi plant for off-site treatment and final material disposition.

The operator received a unified closure package covering all four sites, with consistent documentation across the project rather than four separate files. The package supported the operator’s asset records, regulatory closure for each site, and the financial accounting for the asset retirement.

Fleet retirement work tends to cluster — a utility that has one aging station usually has several. The Nebraska campaign was planned as four sites from the start. Operators planning similar work generally save time and budget by scoping the full retirement before any individual site begins.

Upward view of a modern high-rise apartment tower in Manhattan with reflective glass windows and protruding balconies against a blue sky.
Manhattan Odor Fade Resolution

Odor fade in the new gas piping of a Manhattan high-rise, eliminated in two weeks with no odorant intentionally released to the neighborhood.

MRR enclosure tent reading "Your End-to-End Gas Odorization Partner," connected to hoses and blower equipment for an atmospheric-isolated soil excavation, with safety cones in the foreground.
Large Mercaptan Spill Remediated

More than 400 odor calls, seven figures a day in potential lost revenue, and mercaptan underground beside active waterways.

Small tan modular gas odorization building connected to storage tanks and piping at a rural renewable natural gas site, with utility poles in the background.
RNG Building, 3-Month Commission

A modular RNG odorization building, manufactured off-site and commissioned at a Quebec injection point on a three-month schedule.

Technician in blue coveralls with reflective safety striping adjusting a temporary gas odorization skid and tank at a fenced outdoor site.
Emergency Temporary Odorization

Maintaining odorization compliance for three months while a failed permanent system was redesigned, fabricated, and installed.

Refinery storage tank being decommissioned at an industrial site in Illinois.
5,000-Gallon Tank Decommissioning

Replacing a 5,000-gallon ethyl mercaptan tank at a refinery, with 1,800 gallons of odorant held and returned to service.

On-site incineration equipment used to drain and treat over-odorized liquid from a 12-inch transmission line in Quebec
12-Inch Odorant Drain and Incineration

Excavating, tapping, and draining liquid odorant from a 12-inch transmission line — two-week response with on-site incineration.

C1D1-rated dual-odorizer trailer, a custom-built mobile gas odorization unit, at an industrial site in Illinois.
C1D1 Dual-Odorizer Trailer

A dual-odorizer trailer with integrated filtration, flow telemetry, and C1D1-rated systems — 20 weeks from order to delivery.

Row of portable flare units operating at night to generate flow for an inline pipeline inspection campaign in northern Ontario
Six-Week Flow Generation

Portable flow generation supporting an inline inspection campaign in northern Ontario — 12 to 16 hours a day across six weeks.

Natural gas pipeline conditioning equipment at a shopping mall construction site in New Jersey.
New Jersey Mall Gas Line Conditioning

Conditioning new gas lines inside a mall under construction — with continuous monitoring that surfaced previously undetected leaks.

1,000-gallon modular gas odorization building installed at a site in Georgia.
1,000-Gallon Modular Building

A 1,000-gallon modular odorization building, fabricated at the MRR shop and set on its foundation as a single integrated unit.

Natural gas odorization equipment being decommissioned across four stations at a site in Nebraska.
Four-Station Retirement, 2,300 Gal.

Retiring odorization infrastructure across four stations, recovering 2,300 gallons of odorant for continued service.

Storage tanks being decommissioned following a lightning-strike fire at a natural gas site in Alabama.
Three-Tank Decommissioning

Stabilizing and decommissioning three tanks damaged in a suspected lightning-strike fire, four days from mobilization to closure.

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
5-Month RNG Commission

Custom design, manufacturing, and commissioning of a renewable natural gas odorization system, delivered in five months end to end.

1980s-era underground storage tank being cut down and removed at a site in Michigan.
1980s Tank Removal

Removing a 1980s-era underground bulk odorant tank too large to transport — treated and cut down for removal entirely on site.

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
36-Inch, 10-Week Pickling at 850 psig

Conditioning a new 36-inch, 64-mile transmission pipeline over 10 weeks of continuous online pickling at 850 psig.