1,000-Gallon Modular Building

Stories

1,000-gallon modular gas odorization building installed at a site in Georgia.
Share
Georgia, USA
MRR-1000 modular building
Six-month project

A natural gas utility in Georgia needed a new odorization installation at a gate station — capacity to support the station’s flow requirements, full secondary containment, environmental controls suitable for the regional climate, and a footprint that fit within the operator’s site constraints. Building the equipment in place at the gate station would have required an extended on-site construction window with all the associated permitting, traffic control, and operational disruption that accompanies multi-week field work at an operating station. The operator needed a different model. Off-site fabrication, on-site placement.

Approach

MRR delivered the project as a modular building solution — a complete 1,000-gallon odorization facility constructed at the MRR plant and shipped to the Georgia site as a single integrated unit.

The construction phase took place under controlled conditions at the MRR plant. The building was fabricated to the engineered specification, the odorant storage tank was installed within its secondary containment, the odorizer equipment was mounted and connected, the environmental controls and lighting were installed, and the unit was tested as a complete system before shipment. This compressed the on-site exposure of the project from the multi-week duration of stick-built construction down to the placement and tie-in duration.

Transport from the plant to the Georgia site was handled under the load classification appropriate to the unit. On-site placement required crane work to set the building on its prepared foundation. Once in place, MRR field crews completed the connections to the operator’s gas piping and electrical systems, performed the leak testing and pressure testing, took the initial odorant delivery, and commissioned the unit.

The full project — design, fabrication, transport, placement, commissioning, and operator training — ran approximately six months from order to operational handover.

Outcome

The Georgia gate station received a fully integrated, factory-tested odorization facility with minimal site disruption during placement. The operator’s documentation package included the manufacturing records from MRR’s shop, the engineered drawings, the commissioning report, and the operating manuals.

The modular approach reduced the operator's on-site project management overhead and helped reduce schedule and weather-related risks while supporting controlled fabrication quality.

MRR manufactures modular buildings, tanks, skids, and trailers at the company’s facilities in Summerstown, Ontario, and at the plant in Philippi, West Virginia. The Georgia building was one of several modular units shipped from the shop in the same period — each engineered to a specific customer site, each delivered as a finished unit ready for placement.

Upward view of a modern high-rise apartment tower in Manhattan with reflective glass windows and protruding balconies against a blue sky.
Manhattan Odor Fade Resolution

Odor fade in the new gas piping of a Manhattan high-rise, eliminated in two weeks with no odorant intentionally released to the neighborhood.

MRR enclosure tent reading "Your End-to-End Gas Odorization Partner," connected to hoses and blower equipment for an atmospheric-isolated soil excavation, with safety cones in the foreground.
Large Mercaptan Spill Remediated

More than 400 odor calls, seven figures a day in potential lost revenue, and mercaptan underground beside active waterways.

Small tan modular gas odorization building connected to storage tanks and piping at a rural renewable natural gas site, with utility poles in the background.
RNG Building, 3-Month Commission

A modular RNG odorization building, manufactured off-site and commissioned at a Quebec injection point on a three-month schedule.

Technician in blue coveralls with reflective safety striping adjusting a temporary gas odorization skid and tank at a fenced outdoor site.
Emergency Temporary Odorization

Maintaining odorization compliance for three months while a failed permanent system was redesigned, fabricated, and installed.

Refinery storage tank being decommissioned at an industrial site in Illinois.
5,000-Gallon Tank Decommissioning

Replacing a 5,000-gallon ethyl mercaptan tank at a refinery, with 1,800 gallons of odorant held and returned to service.

On-site incineration equipment used to drain and treat over-odorized liquid from a 12-inch transmission line in Quebec
12-Inch Odorant Drain and Incineration

Excavating, tapping, and draining liquid odorant from a 12-inch transmission line — two-week response with on-site incineration.

C1D1-rated dual-odorizer trailer, a custom-built mobile gas odorization unit, at an industrial site in Illinois.
C1D1 Dual-Odorizer Trailer

A dual-odorizer trailer with integrated filtration, flow telemetry, and C1D1-rated systems — 20 weeks from order to delivery.

Row of portable flare units operating at night to generate flow for an inline pipeline inspection campaign in northern Ontario
Six-Week Flow Generation

Portable flow generation supporting an inline inspection campaign in northern Ontario — 12 to 16 hours a day across six weeks.

Natural gas pipeline conditioning equipment at a shopping mall construction site in New Jersey.
New Jersey Mall Gas Line Conditioning

Conditioning new gas lines inside a mall under construction — with continuous monitoring that surfaced previously undetected leaks.

1,000-gallon modular gas odorization building installed at a site in Georgia.
1,000-Gallon Modular Building

A 1,000-gallon modular odorization building, fabricated at the MRR shop and set on its foundation as a single integrated unit.

Natural gas odorization equipment being decommissioned across four stations at a site in Nebraska.
Four-Station Retirement, 2,300 Gal.

Retiring odorization infrastructure across four stations, recovering 2,300 gallons of odorant for continued service.

Storage tanks being decommissioned following a lightning-strike fire at a natural gas site in Alabama.
Three-Tank Decommissioning

Stabilizing and decommissioning three tanks damaged in a suspected lightning-strike fire, four days from mobilization to closure.

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
5-Month RNG Commission

Custom design, manufacturing, and commissioning of a renewable natural gas odorization system, delivered in five months end to end.

1980s-era underground storage tank being cut down and removed at a site in Michigan.
1980s Tank Removal

Removing a 1980s-era underground bulk odorant tank too large to transport — treated and cut down for removal entirely on site.

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
36-Inch, 10-Week Pickling at 850 psig

Conditioning a new 36-inch, 64-mile transmission pipeline over 10 weeks of continuous online pickling at 850 psig.