RNG Building, 3-Month Commission

Stories

Small tan modular gas odorization building connected to storage tanks and piping at a rural renewable natural gas site, with utility poles in the background.
Share
Quebec, CAN
Modular RNG odorization building
Three-month project

A renewable natural gas producer in Quebec was bringing a new injection point online and needed an odorization installation matched to the site’s flow profile, environmental conditions, and regulatory requirements. The injection point’s location, the producer’s site constraints, and the timeline pressure of an RNG project ramping toward commercial operation all argued for a modular building rather than field-built construction.

The producer needed an odorization installation that would be in place, commissioned, and operating in time for the broader RNG facility to begin commercial gas injection. Equipment selection, manufacturing, transport, installation, and commissioning all had to fit within the three-month window the project schedule allowed.

Approach

MRR delivered the project as an integrated modular installation. The odorization building was specified to match the site’s gas flow profile, configured with the storage capacity appropriate to the operator’s preferred service interval, and engineered to operate reliably through Quebec winters and the temperature swings of the surrounding agricultural environment.

The building was manufactured at the MRR plant under controlled conditions, with the odorant storage tank, injection equipment, monitoring system, secondary containment, and environmental controls all installed and tested as a complete system before shipment.

Manufacturing the building off-site rather than in the field reduced the on-site construction footprint and compressed the project schedule.

On arrival at the Quebec site, the building was set on its prepared foundation. MRR field crews completed the tie-ins to the producer’s upstream gas processing equipment and downstream pipeline, performed the leak testing and pressure testing, took the initial odorant delivery, and commissioned the system. Operator training was delivered during commissioning, covering routine operation, scheduled maintenance, and the response protocols for the equipment’s monitoring alarms.

The full project — design coordination, manufacturing, transport, placement, commissioning, and operator training — ran approximately three months from project kickoff to operational handover.

Outcome

The Quebec RNG injection point received a fully commissioned, factory-tested odorization building that integrated cleanly with the producer’s upstream and downstream equipment.

The producer transitioned to commercial gas injection on schedule, with odorant concentration verified against the operator's commissioning criteria from the first day of operation. The documentation package — design records, manufacturing records, commissioning report, operating manuals, and operator training records — gave the producer the foundation for the regulatory and operational records the asset will accumulate over its service life.

The Quebec project is one of several RNG odorization installations MRR has delivered in the region, each engineered to the specific characteristics of its site rather than retrofitted from a generic equipment package.

Upward view of a modern high-rise apartment tower in Manhattan with reflective glass windows and protruding balconies against a blue sky.
Manhattan Odor Fade Resolution

Odor fade in the new gas piping of a Manhattan high-rise, eliminated in two weeks with no odorant intentionally released to the neighborhood.

MRR enclosure tent reading "Your End-to-End Gas Odorization Partner," connected to hoses and blower equipment for an atmospheric-isolated soil excavation, with safety cones in the foreground.
Large Mercaptan Spill Remediated

More than 400 odor calls, seven figures a day in potential lost revenue, and mercaptan underground beside active waterways.

Small tan modular gas odorization building connected to storage tanks and piping at a rural renewable natural gas site, with utility poles in the background.
RNG Building, 3-Month Commission

A modular RNG odorization building, manufactured off-site and commissioned at a Quebec injection point on a three-month schedule.

Technician in blue coveralls with reflective safety striping adjusting a temporary gas odorization skid and tank at a fenced outdoor site.
Emergency Temporary Odorization

Maintaining odorization compliance for three months while a failed permanent system was redesigned, fabricated, and installed.

Refinery storage tank being decommissioned at an industrial site in Illinois.
5,000-Gallon Tank Decommissioning

Replacing a 5,000-gallon ethyl mercaptan tank at a refinery, with 1,800 gallons of odorant held and returned to service.

On-site incineration equipment used to drain and treat over-odorized liquid from a 12-inch transmission line in Quebec
12-Inch Odorant Drain and Incineration

Excavating, tapping, and draining liquid odorant from a 12-inch transmission line — two-week response with on-site incineration.

C1D1-rated dual-odorizer trailer, a custom-built mobile gas odorization unit, at an industrial site in Illinois.
C1D1 Dual-Odorizer Trailer

A dual-odorizer trailer with integrated filtration, flow telemetry, and C1D1-rated systems — 20 weeks from order to delivery.

Row of portable flare units operating at night to generate flow for an inline pipeline inspection campaign in northern Ontario
Six-Week Flow Generation

Portable flow generation supporting an inline inspection campaign in northern Ontario — 12 to 16 hours a day across six weeks.

Natural gas pipeline conditioning equipment at a shopping mall construction site in New Jersey.
New Jersey Mall Gas Line Conditioning

Conditioning new gas lines inside a mall under construction — with continuous monitoring that surfaced previously undetected leaks.

1,000-gallon modular gas odorization building installed at a site in Georgia.
1,000-Gallon Modular Building

A 1,000-gallon modular odorization building, fabricated at the MRR shop and set on its foundation as a single integrated unit.

Natural gas odorization equipment being decommissioned across four stations at a site in Nebraska.
Four-Station Retirement, 2,300 Gal.

Retiring odorization infrastructure across four stations, recovering 2,300 gallons of odorant for continued service.

Storage tanks being decommissioned following a lightning-strike fire at a natural gas site in Alabama.
Three-Tank Decommissioning

Stabilizing and decommissioning three tanks damaged in a suspected lightning-strike fire, four days from mobilization to closure.

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
5-Month RNG Commission

Custom design, manufacturing, and commissioning of a renewable natural gas odorization system, delivered in five months end to end.

1980s-era underground storage tank being cut down and removed at a site in Michigan.
1980s Tank Removal

Removing a 1980s-era underground bulk odorant tank too large to transport — treated and cut down for removal entirely on site.

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
36-Inch, 10-Week Pickling at 850 psig

Conditioning a new 36-inch, 64-mile transmission pipeline over 10 weeks of continuous online pickling at 850 psig.