5-Month RNG Commission

Stories

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
Share
Ontario, CAN
Custom RNG odorizer
Design, build, and commission
Five-month project

A renewable natural gas producer in Ontario was preparing to bring a new injection point online and required an odorization system engineered specifically for the project’s site conditions, gas composition, and operational requirements. Off-the-shelf equipment was not the right answer. The producer needed a custom-designed odorizer that would meet provincial regulatory requirements, integrate cleanly with the upstream gas upgrading equipment and downstream pipeline tie-in, operate reliably through Ontario winters, and support the long-term service intervals appropriate to an RNG injection facility.

The project demanded engineering capability beyond installation: design from the producer’s specification, fabrication to the design, and a commissioning process that would hand the operator a working, documented, code-compliant system.

Approach

MRR delivered the project as a full design-build-commission scope over five months.

The design phase produced a custom odorizer engineered around the specific gas flow profile and odorant blend selected for the injection point. The design covered the odorant storage tank specification, the injection equipment, the monitoring and control system, the secondary containment and enclosure structure, and the integration points with the producer's upstream and downstream equipment. The unit was engineered to meet TSSA requirements. Engineered drawings were issued as part of the design deliverable, ensuring the producer's project team and the regulator had clear documentation of the system being installed.

Construction took place at MRR’s manufacturing facility. Building the equipment off-site rather than on-site reduced field labor, allowed quality control to happen under controlled conditions, and shortened the on-site installation window to a fraction of what an entirely field-built system would have required. All tubing was orbitally welded for cleanliness and long-term reliability. The complete unit was tested at the MRR facility before shipment.

On-site installation, commissioning, and the initial odorant delivery were performed by MRR field crews. The producer’s operating team received hands-on training during commissioning, covering routine operation, scheduled maintenance, and the response protocols for the equipment’s monitoring alarms.

Outcome

The RNG odorizer was commissioned on schedule and entered service supporting the producer's injection operations. At commissioning, the system's detectability performance met the requirements of CSA Z662 and the provincial pipeline safety regulations applicable to the site. The engineered drawings, the manufacturing records, the commissioning report, and the operating manuals together formed the project closure package — the documentation foundation the producer relies on for regulatory compliance, future maintenance planning, and any future modifications to the system.

The project demonstrates the supply-side support that the RNG sector increasingly requires. Each new injection point becomes a new odorization point. Producers building RNG infrastructure need partners who can engineer to the specific characteristics of each site rather than retrofit a generic equipment package.

The supply-side work — engineering, building, commissioning, supporting — has grown with it. The Ontario unit is one of a growing fleet of MRR-engineered RNG odorizers across the continent.

Upward view of a modern high-rise apartment tower in Manhattan with reflective glass windows and protruding balconies against a blue sky.
Manhattan Odor Fade Resolution

Odor fade in the new gas piping of a Manhattan high-rise, eliminated in two weeks with no odorant intentionally released to the neighborhood.

MRR enclosure tent reading "Your End-to-End Gas Odorization Partner," connected to hoses and blower equipment for an atmospheric-isolated soil excavation, with safety cones in the foreground.
Large Mercaptan Spill Remediated

More than 400 odor calls, seven figures a day in potential lost revenue, and mercaptan underground beside active waterways.

Small tan modular gas odorization building connected to storage tanks and piping at a rural renewable natural gas site, with utility poles in the background.
RNG Building, 3-Month Commission

A modular RNG odorization building, manufactured off-site and commissioned at a Quebec injection point on a three-month schedule.

Technician in blue coveralls with reflective safety striping adjusting a temporary gas odorization skid and tank at a fenced outdoor site.
Emergency Temporary Odorization

Maintaining odorization compliance for three months while a failed permanent system was redesigned, fabricated, and installed.

Refinery storage tank being decommissioned at an industrial site in Illinois.
5,000-Gallon Tank Decommissioning

Replacing a 5,000-gallon ethyl mercaptan tank at a refinery, with 1,800 gallons of odorant held and returned to service.

On-site incineration equipment used to drain and treat over-odorized liquid from a 12-inch transmission line in Quebec
12-Inch Odorant Drain and Incineration

Excavating, tapping, and draining liquid odorant from a 12-inch transmission line — two-week response with on-site incineration.

C1D1-rated dual-odorizer trailer, a custom-built mobile gas odorization unit, at an industrial site in Illinois.
C1D1 Dual-Odorizer Trailer

A dual-odorizer trailer with integrated filtration, flow telemetry, and C1D1-rated systems — 20 weeks from order to delivery.

Row of portable flare units operating at night to generate flow for an inline pipeline inspection campaign in northern Ontario
Six-Week Flow Generation

Portable flow generation supporting an inline inspection campaign in northern Ontario — 12 to 16 hours a day across six weeks.

Natural gas pipeline conditioning equipment at a shopping mall construction site in New Jersey.
New Jersey Mall Gas Line Conditioning

Conditioning new gas lines inside a mall under construction — with continuous monitoring that surfaced previously undetected leaks.

1,000-gallon modular gas odorization building installed at a site in Georgia.
1,000-Gallon Modular Building

A 1,000-gallon modular odorization building, fabricated at the MRR shop and set on its foundation as a single integrated unit.

Natural gas odorization equipment being decommissioned across four stations at a site in Nebraska.
Four-Station Retirement, 2,300 Gal.

Retiring odorization infrastructure across four stations, recovering 2,300 gallons of odorant for continued service.

Storage tanks being decommissioned following a lightning-strike fire at a natural gas site in Alabama.
Three-Tank Decommissioning

Stabilizing and decommissioning three tanks damaged in a suspected lightning-strike fire, four days from mobilization to closure.

Renewable natural gas odorization system engineered and commissioned at a site in Ontario.
5-Month RNG Commission

Custom design, manufacturing, and commissioning of a renewable natural gas odorization system, delivered in five months end to end.

1980s-era underground storage tank being cut down and removed at a site in Michigan.
1980s Tank Removal

Removing a 1980s-era underground bulk odorant tank too large to transport — treated and cut down for removal entirely on site.

36-inch natural gas transmission line during a pipeline pickling operation at a site in Texas.
36-Inch, 10-Week Pickling at 850 psig

Conditioning a new 36-inch, 64-mile transmission pipeline over 10 weeks of continuous online pickling at 850 psig.